Timeline

The Greek Village Master Plan (pdf) calls for a phased redevelopment of the current Greek housing area into a vibrant neighborhood at the heart of the NC State campus. The plan, originally designed by Sam Reynolds of Reynolds & Jewell Architects in 2006, has been refined slightly by Stewart Engineering, but maintains all the core elements of set forth by the Greek Court Redevelopment Task Force. The Village will contain 20 lots for individual chapter houses, a row of Greek Townhouses, a community center, amphitheatre, outdoor shelters, and other attractive amenities. Greek Village will be developed in 5 phases (pdf) beginning in 2008 with a target completion date of 2022.

Phasing Details

This timeline for phasing has been adjusted from Phase 2 down to adjust for econimic impacts (loss of state funding for one year) to the project. This one year delay has not lessened our commitment to the project as we are still moving forward with townhouse design and have restored university/state funding to the project.

Choose any phase image for a full-size version.

Phase 1 LayoutPhase 1: 2008-2014 (pdf)

  • Chapters begin construction September 2011
  • First houses open Fall 2012 to Fall 2014

 

 

Phase 2 LayoutPhase 2: 2013-2016 (pdf)

  • Earnest money and Greek Village Letter of Commitments received from Sigma Chi for Lot 20 and Delta Zeta for Lot 19
  • Need progress in Phase 1 to proceed
  • Demolition of Pi Kappa Phi, Sigma Nu and Sigma Phi Epsilon May 2013
  • Infrastructure work to begin June 2013
  • University begins construction of townhomes and apartments in June 2014
  • Chapters begin construction June 2014
  • Houses, Townhomes and Apartments open Fall 2015 to Fall 2016
 

Phase 3 LayoutPhase 3: 2015-2018 (pdf)

  • Earnest money and Greek Village Letter of Commitments received from Alpha Delta Pi for Lot 8, Pi Kappa Phi and Lambda Chi Alpha for Lot 9, and Delta Delta Delta for Lot 10. The Greek Village Housing Association will determine final assignment of Lot 9.
  • Demolition of Pi Kappa Alpha, Delta Gamma and Alpha Sigma Phi May 2015
  • Infrastructure work to begin June 2015
  • Chapters begin construction August 2016
  • Houses open Fall 2017 to Fall 2018
 

Phase 4 LayoutPhase 4: 2017-2020 (pdf)

  • Earnest money and Greek Village Letter of Commitment for Lots 11-18 no sooner than May 1, 2012 and no later than August 1, 2012
  • Need commitments from eight chapters and progress on previous phases to proceed
  • Demolition of  Kappa Sigma, Delta Delta Delta, Delta Zeta and MEAS Storage buildings May 2017
  • Infrastructure work to begin June 2017
  • Chapters begin construction August 2018
  • Houses open Fall 2019 to Fall 2020
 

Phase 5 LayoutPhase 5: 2019-2022 (pdf)

  • Earnest money and Greek Village Letter of Commitment for Lots 5-7 no sooner than May 1, 2012 and no later than August 1, 2012
  • Need commitments from three chapters and progress on previous phases to proceed
  • Demolition of Sorority Duplex and Entomology Lab May 2019
  • Infrastructure work to begin June 2019
  • Chapters begin construction August 2020
  • Houses open Fall 2021 to Fall 2022
  • Demolition of house 8 (currently Alpha Delta Pi) Summer 2021

Common Amenities: